Skip to content
Study Notes/Civil Engineering/Construction Management

Construction Management

Project planning, scheduling, cost estimation, and site management

1. Project Planning Fundamentals

Project Management Triangle

Balancing scope, time, and cost while maintaining quality. Changing one affects the others.

Project Life Cycle

1. Initiation

Feasibility study, project charter, stakeholder identification

2. Planning

WBS, scheduling, budgeting, resource planning

3. Execution

Construction, monitoring, quality control

4. Closeout

Final inspection, handover, documentation

Work Breakdown Structure (WBS)

Hierarchical decomposition of project scope into manageable work packages.

Level 1: Project

Level 2: Phases (Foundation, Superstructure, MEP, Finishes)

Level 3: Deliverables (Footings, Columns, Beams)

Level 4: Work Packages (Excavation, Formwork, Reinforcement)

Project Delivery Methods

MethodDescriptionAdvantages
Design-Bid-BuildSequential: Design → Bid → BuildClear scope, competitive pricing
Design-BuildSingle entity for design and constructionFaster, single point of responsibility
CM at RiskCM guarantees maximum priceEarly CM input, cost certainty
Build-Operate-TransferPrivate builds, operates, then transfersInfrastructure financing

2. CPM and PERT Scheduling

Network Scheduling Techniques

CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) are essential for project scheduling.

Activity Relationships

Finish-to-Start (FS)

Most common. B starts after A finishes.

Start-to-Start (SS)

B starts when A starts (with lag).

Finish-to-Finish (FF)

B finishes when A finishes.

Start-to-Finish (SF)

Rare. B finishes when A starts.

CPM Calculations

Forward Pass (Early Times)

ES = max(EF of predecessors)

EF = ES + Duration

Backward Pass (Late Times)

LF = min(LS of successors)

LS = LF - Duration

Float/Slack Calculations

Total Float (TF)

TF = LS - ES = LF - EF

Time activity can be delayed without delaying project

Free Float (FF)

FF = ES(successor) - EF(current)

Time activity can be delayed without delaying successor

Critical Path

Critical Path = Longest path through network = Total Float of 0

  • • Determines minimum project duration
  • • Any delay on critical path delays project
  • • Focus resources on critical activities
  • • May have multiple critical paths

PERT (Probabilistic Approach)

Three-Time Estimate

a

Optimistic

m

Most Likely

b

Pessimistic

te = (a + 4m + b) / 6

Expected time (Beta distribution)

σ = (b - a) / 6

Standard deviation of activity

Project Duration Probability

σproject = √(Σσ²critical)

Sum variances along critical path

Z = (Ts - Te) / σproject

Ts = scheduled time, Te = expected time

3. Bar Charts and Scheduling Tools

Gantt Chart (Bar Chart)

Characteristics:

  • • Horizontal bars showing activity duration
  • • Time scale on horizontal axis
  • • Activities listed on vertical axis
  • • Easy to understand and communicate
  • • Limited for showing dependencies

S-Curve (Progress Curve)

Types of S-Curves:

  • Planned S-Curve: Baseline cumulative progress over time
  • Actual S-Curve: Actual cumulative progress to date
  • Earned Value S-Curve: Value of work completed

Shape reflects typical project progress: slow start, rapid middle, slow finish

Resource Leveling

Adjusting activity schedules to optimize resource utilization while respecting constraints.

Time-Constrained

Fixed deadline, variable resources

Resource-Constrained

Limited resources, variable duration

Line of Balance (LOB)

Used for repetitive projects (highways, high-rise floors)

  • • Shows production rate for each activity
  • • Slope of line = rate of progress
  • • Parallel lines indicate balanced resources
  • • Identifies buffers needed between activities

Schedule Compression

Crashing

Add resources to critical activities

  • • Increases direct costs
  • • Crash critical path first
  • • Use lowest cost slope

Cost Slope = (Crash Cost - Normal Cost)/(Normal Time - Crash Time)

Fast Tracking

Perform activities in parallel

  • • No additional cost (typically)
  • • Increases risk
  • • May require rework

4. Cost Estimation

Types of Estimates

TypeAccuracyPurpose
Order of Magnitude-30% to +50%Feasibility, conceptual
Preliminary-15% to +30%Budgeting, schematic
Definitive-5% to +15%Bidding, detailed design

Cost Components

Direct Costs

  • • Labor
  • • Materials
  • • Equipment
  • • Subcontractors

Indirect Costs

  • • Overhead (office, insurance)
  • • Supervision
  • • Temporary facilities
  • • General conditions

Quantity Takeoff

Common Units:

  • • Concrete: cubic meters (m³)
  • • Reinforcing steel: kilograms (kg)
  • • Formwork: square meters (m²)
  • • Excavation: cubic meters (m³)
  • • Painting: square meters (m²)
  • • Electrical/Plumbing: points or meters

Unit Price Analysis

Unit Price = Labor + Materials + Equipment + Overhead + Profit

Labor: (Crew hours × Wage rate) / Output

Materials: Quantity × Unit cost + Waste allowance

Equipment: Ownership + Operating costs

Markup: Typically 10-20% for overhead, 5-15% for profit

Earned Value Management (EVM)

PV (BCWS)

Planned Value

EV (BCWP)

Earned Value

AC (ACWP)

Actual Cost

Variances:

Schedule Variance (SV) = EV - PV

Cost Variance (CV) = EV - AC

Positive = favorable, Negative = unfavorable

Performance Indices:

Schedule Performance Index (SPI) = EV / PV

Cost Performance Index (CPI) = EV / AC

>1.0 = ahead/under, <1.0 = behind/over

5. Construction Contracts

Contract Types

Lump Sum (Fixed Price)

  • • Contractor bears most risk
  • • Fixed price for defined scope
  • • Best when scope is well-defined
  • • Encourages cost efficiency

Unit Price

  • • Payment based on quantities
  • • Risk shared between parties
  • • Good when quantities uncertain
  • • Common for infrastructure projects

Cost Plus (Cost Reimbursable)

  • • Owner bears most risk
  • • Contractor paid actual cost + fee
  • • Used when scope uncertain
  • • Variations: Cost + Fixed Fee, Cost + Percentage

Guaranteed Maximum Price (GMP)

  • • Cost plus with ceiling
  • • Owner pays actual cost up to GMP
  • • Savings often shared
  • • Common with CM at Risk

Contract Documents

Order of Precedence (typical):

  1. Agreement
  2. Addenda
  3. Special Conditions
  4. General Conditions
  5. Specifications
  6. Drawings

Change Orders

Types of Changes:

  • Owner-Directed: Scope changes requested by owner
  • Differing Site Conditions: Unforeseen subsurface conditions
  • Design Errors: Corrections to drawings/specs
  • Regulatory Changes: New code requirements

Process: Request → Review → Negotiate → Approve → Execute

Philippine Bidding Law (RA 9184)

Key Provisions:

  • • Competitive bidding is default procurement method
  • • Single calculated and responsive bid acceptable
  • • Ceiling price based on Approved Budget for Contract (ABC)
  • • Lowest Calculated Responsive Bid wins
  • • Alternative methods: Limited Source, Direct Contracting, Shopping

6. Construction Safety

Safety is Priority

Construction is one of the most hazardous industries. DOLE-OSH standards and DENR regulations apply.

Hierarchy of Controls

  1. Elimination: Remove the hazard entirely
  2. Substitution: Replace with less hazardous alternative
  3. Engineering Controls: Isolate people from hazard
  4. Administrative Controls: Change work procedures
  5. PPE: Personal Protective Equipment (last resort)

Common Hazards

Fatal Four (OSHA)

  • • Falls (leading cause)
  • • Struck by object
  • • Electrocution
  • • Caught in/between

Other Hazards

  • • Excavation collapse
  • • Scaffold failures
  • • Heavy equipment
  • • Hazardous materials

Fall Protection

Required at 6 feet (1.8m) or more in general construction

  • • Guardrails: Top rail at 42" (1.07m), mid rail, toe board
  • • Safety nets: Within 30 feet of work
  • • Personal fall arrest: Anchor, connector, body harness
  • • Hole covers: Capable of supporting 2× expected load

Excavation Safety

Protection required at 4 feet (1.2m) or more depth

  • Sloping: Cut back trench walls at safe angle (1:1 for Type B soil)
  • Benching: Series of horizontal levels
  • Shoring: Support systems (timber, hydraulic, aluminum)
  • Shielding: Trench boxes to protect workers

Safety Metrics

Incidence Rate = (N × 200,000) / Hours Worked

N = number of injuries/illnesses, 200,000 = 100 full-time workers

Severity Rate = (Lost Days × 200,000) / Hours Worked

Measures impact of injuries

Frequency Rate = (Lost Time Injuries × 1,000,000) / Hours Worked

7. Quality Control and Assurance

QA vs QC

Quality Assurance (QA)

Preventive: Processes to ensure quality

Quality Control (QC)

Corrective: Testing to verify quality

Concrete Quality Control

Common Tests:

  • Slump Test: Workability (typical 75-100mm for structural)
  • Compressive Test: 150mm cubes or 150×300mm cylinders at 7, 28 days
  • Air Content: Pressure method, typically 4-7% for durability
  • Temperature: Should not exceed 32°C at placement

Acceptance Criteria (NSCP):

  • • Average of 3 tests ≥ f'c
  • • No single test < f'c - 3.5 MPa (for f'c ≤ 35 MPa)

Steel Testing

  • Tensile Test: Yield strength, ultimate strength, elongation
  • Bend Test: Ductility, 180° bend without cracking
  • Chemical Analysis: Carbon, manganese, sulfur content
  • Mill Certificates: Required for structural steel

Soil Testing (Field)

  • Field Density Test: Sand cone, nuclear density gauge
  • Plate Load Test: Bearing capacity verification
  • SPT (Standard Penetration Test): N-value for soil strength
  • DCP (Dynamic Cone Penetrometer): Quick subgrade assessment

Quality Tools

Seven Basic QC Tools

  1. Check sheets
  2. Histograms
  3. Pareto charts
  4. Cause-and-effect (Fishbone)
  5. Scatter diagrams
  6. Control charts
  7. Flowcharts

Inspection Types

  • Pre-pour: Before concrete placement
  • In-process: During construction
  • Final: Completion inspection
  • Third-party: Independent verification

8. Professional Practice and Ethics

Civil Engineering Law (RA 544)

Key Provisions:

  • • Only licensed CEs may practice civil engineering
  • • Board of Civil Engineering regulates profession
  • • Seal required on all CE documents
  • • CPD (Continuing Professional Development) required

Code of Ethics

Fundamental Canons:

  1. Hold paramount the safety, health, and welfare of the public
  2. Perform services only in areas of competence
  3. Issue public statements only in objective and truthful manner
  4. Act as faithful agent or trustee for each employer/client
  5. Avoid deceptive acts
  6. Conduct themselves honorably and responsibly

National Building Code (PD 1096)

Key Requirements:

  • • Building permit required before construction
  • • Occupancy permit required before use
  • • Fire safety requirements (RA 9514)
  • • Accessibility requirements (BP 344)
  • • Zoning compliance

Environmental Compliance

Requirements (DENR):

  • ECC: Environmental Compliance Certificate for major projects
  • EIS: Environmental Impact Statement
  • IEE: Initial Environmental Examination
  • CNC: Certificate of Non-Coverage for small projects

Insurance and Bonds

  • Bid Bond: 1-5% of bid, ensures serious bidders
  • Performance Bond: 100% of contract, ensures completion
  • Payment Bond: Ensures payment to subcontractors/suppliers
  • Retention: Typically 5-10% held until final acceptance
  • CAR Insurance: Contractor's All Risk, covers project damage
  • Professional Liability: Errors and omissions coverage

Dispute Resolution

  1. Negotiation: Direct discussion between parties
  2. Mediation: Neutral third party facilitates agreement
  3. Arbitration: Binding decision by arbitrator(s)
  4. Litigation: Court proceedings (last resort)

CIAC (Construction Industry Arbitration Commission) handles construction disputes in the Philippines

Key Takeaways for CE Board Exam

Must-Know Formulas

  • ✓ Total Float: TF = LS - ES = LF - EF
  • ✓ PERT Expected Time: te = (a + 4m + b)/6
  • ✓ PERT Variance: σ² = [(b-a)/6]²
  • ✓ Cost Variance: CV = EV - AC
  • ✓ Schedule Variance: SV = EV - PV
  • ✓ CPI = EV/AC, SPI = EV/PV
  • ✓ Incidence Rate = (N × 200,000)/Hours

Critical Concepts

  • ✓ Critical Path = Zero float activities
  • ✓ Forward pass (ES, EF) then Backward pass (LS, LF)
  • ✓ Contract types and risk allocation
  • ✓ Crashing vs Fast Tracking
  • ✓ Hierarchy of Safety Controls
  • ✓ QA (preventive) vs QC (corrective)
  • ✓ RA 544, PD 1096, RA 9184 provisions